Solar Developer’s Plea for Extending Project Commissioning Deadline Rejected

The Commission rejected the developer’s request for repayment of the bank guarantee encashed by the DISCOM

thumbnail

The Tamil Nadu Electricity Regulatory Commission (TNERC) has rejected a plea by a solar developer seeking an extension of 18 months for commissioning a project citing ‘force majeure’ events.

The Commission rejected the petition filed by VSR Solar Power seeking a direction to the Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) to repay the bank guarantee already encashed by it for the delay in commissioning of a 50 MW project.

The company had sought an extension of 18 months from March 21, 2019, to September 21, 2020, under the power purchase agreement (PPA) dated March 22, 2018. It had requested the Commission to pay ₹51 million (~$701,432) encashed by TANGEDCO as a bank guarantee.

Background

TANGEDCO had floated a tender to procure 1,500 MW of solar power from the developers establishing solar power plants in Tamil Nadu under the reverse bidding process.

After price negotiation, 16 developers with a combined capacity of 1500 MW were finalized by TANGEDCO for supplying solar power at the rate of ₹3.47 (~$0.047)/kWh on a long term basis.

The successful bidders executed PPAs with TANGEDCO within the stipulated time except for SaiJyothi Infrastructure Ventures (54 MW) and Talettutayi Solar Project Two (50 MW). Their letters of award (LOAs) were canceled, and the available 104 MW was allotted to four other developers, out of which VSR Solar Power was allotted 50 MW.

Accordingly, TANGEDCO issued a letter of intent to VSR Solar Power to establish a 50 MW solar project at Krishnagiri district, and supply solar power at the rate of ₹3.47 (~$0.047)/kWh. The company subsequently requested a change of location of the project and entered into a PPA to develop the project at Vilathikulam in the Tuticorin district.

Later, the solar developer cited Safeguard Duty’s imposition on imports of solar modules from China, Taiwan, and Malaysia as a ‘change in law’ and a ‘force majeure’ event.

The developer stated that they had been prevented from developing and commissioning the solar power project at Tuticorin district because of a natural disaster that hit Tamil Nadu’s coast in December 2018.

TANGEDCO said that the PPA executed by the developer stood automatically terminated on August 21, 2019, on account of the developer’s failure to commission the project by August 21, 2019. The developer had also not furnished an additional performance bank guarantee to extend the PPA period beyond August 21, 2019.

Commission’s Analysis

After going through all the facts, the Commission noted that when a time limit is prescribed in the PPA for commissioning of the project, the Commission has no power to extend such time limit. The Commission could only examine the parties’ rights and liabilities within the framework of the contract.

The regulator added that the levy of safeguard duty does not fall within the ‘force majeure’ clause. The issue was not whether levy of safeguard duty would come under ‘change in law’ but whether ‘change of law’ would come under ‘force majeure.’

Even assuming that it was a case of ‘change in law,’ the party claiming an event to be a force majeure should within 15 days of such occurrence give notice to the other party in writing. No such letter claiming protection under ‘force majeure’ was provided to TANGEDCO.

The Commission noted that the petitioner had not established the existence of ‘force majeure’ at all more so when all other similarly placed generators had fulfilled their obligation under PPA and commissioned their projects.

“As per the terms of the PPA, if the commissioning of the project is delayed beyond 24 months and up to 29 months, the distribution licensee would encash the bank guarantee on per day basis proportionate to the capacity not commissioned within five months after the expiry of commissioning schedule of 24 months. In case of non-commissioning within 29 months, the distribution licensee would encash the entire 100% bank guarantee,” the Commission noted.

The regulator said that if the commissioning is delayed beyond 29 months and up to 34 months, the solar developer should, in addition to 100% encashment of bank guarantee, pay liquidated damages to the distribution licensee amounting to ₹10,000 (~$137.53)/MW on per day basis in the form of bank guarantee. In case the project is not commissioned within 34 months, the PPA would stand terminated without notice.

Recently, the Ministry of Power drafted new electricity rules to make the compensation process easier for renewable project developers. The draft addresses several important aspects like the change in law and the must-run status of renewables.

In December last year, TNERC rejected a solar developer’s petition to extend the project’s commissioning date. It approved the commissioning of only 50 MW out of the total capacity of 100 MW. It allowed the parties to renegotiate the tariff and enter into a new PPA for the remaining 50 MW.

Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

RELATED POSTS

Get the most relevant India solar and clean energy news.

RECENT POSTS