Solar Developer Asked to Approach SECI to Settle GST Claims Mutually

Petition filed was regarding the compensation for three projects of 130 MW in Maharashtra

thumbnail

The Central Electricity Regulatory Commission (CERC), in a recent order, directed a solar developer to approach the Solar Energy Corporation of India (SECI) to settle the ‘Change in Law’ claims due to the imposition of the goods and services tax (GST) laws.

The affected parties were asked to approach the Commission only to verify the calculation and adjust the amount of the impact in the monthly tariff.

Solar Edge Power and Energy had filed a petition seeking compensation to offset the financial impact of a ‘Change in Law’ event on the development of solar projects due to the imposition of GST laws.

Background

Solar Edge Power and Energy is developing solar projects of a cumulative capacity of 450 MW in Maharashtra.

The solar developer had received a letter from the Maharashtra State Distribution Company Limited (MSEDCL) with respect to the reconciliation of the ‘Change in Law’ claims for three projects of an aggregate capacity of 130 MW.

MSEDCL had raised concerns about two projects for amounts of ₹13,821 (~$182.76) for the 50 MW Parli project and ₹8,353 (~$110.46) for the 30 MW Parli project against the claims of ₹83.3 million (~$1.11 million) and ₹50.7 million (~$670,442).

Later, the Commission directed SECI to confirm that except for the amounts of ₹13,821 (~$182.76) for the 50 MW Parli project and ₹8,353 (~$110.46) for the 30 MW Parli project, as stated by the petitioner, all claims had been reconciled with MSEDCL.

SECI, in its response, communicated the revised provisional reconciliation of the GST claims of the developer for 130 MW projects (50 MW Parli project, 50 MW Muktainagar project, and 30 MW Parli project).

CERC GST Final

The difference in SECI’s evaluation and MSEDCL’s evaluation of the developer’s GST claims was ₹181,008 (~$2,393) concerning the 50 MW Parli project, ₹157,232 (~$2,079) with respect to the 50 MW Muktainagar project, and ₹261,729 (~$3,461) in the 30 MW Parli project.

Commission’s analysis

The Commission observed that as per the ‘Change in Law’ rules, on the occurrence of a ‘Change in Law’ event, the developer and the procurer should settle the compensation claims mutually and approach only in terms of Rule 3(8) of the ‘Change in Law’ rules.

Rule 3(8) states that the appropriate Commission should verify the calculation and adjust the amount of the impact in the monthly tariff or charges within 60 days from the date of receipt of the relevant documents.

The Commission noted that the ‘Change in Law’ rules provided the quantification and methodology for recovering mutually agreed claims relating to the impact of change in the law.

The ‘Change in Law’ rules provides that if there is a formula in the agreement for recovering the impact of the ‘Change in Law,’ it should be applied. Otherwise, the formula prescribed in the ‘Change in Law’ rules should be applied.

The Commission added that the ‘Change in Law’ rules could be applied retrospectively in all pending proceedings.

Recently, CERC directed Tata Power Renewable Energy to approach SECI to mutually settle ‘Change in Law’ claims due to the introduction of GST on solar components.

Earlier, CERC had ruled that power generators and procurers should mutually settle claims under the ‘Change in Law’ provisions. The central regulator had said that the affected parties should approach the Commission only to calculate and verify the amount of compensation.

Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

RELATED POSTS

Get the most relevant India solar and clean energy news.

RECENT POSTS