Solar Federation Requests for Time to Submit Bids for Andhra Pradesh’s 6.4 GW Tender

An extension of three months has been requested

thumbnail

The National Solar Energy Federation of India (NSEFI) has requested the Andhra Pradesh Green Energy Corporation Limited (APGECL) to extend the bid submission deadline for its recent tender for 6.4 GW of grid-connected solar power projects by three months.

Earlier this month, APGECL invited bids for developing 6.4 GW of solar power projects at ten locations in the state. The total capacity of 6.4 GW will include 600 MW at Chakrayapet, 400 MW at Thondur, 600 MW at Kambaldinne, 600 MW at Pendlimarri, 600 MW at Rudrasamudram, 600 MW at CS Puram, 600 MW at Uruchinatala, 1,200 MW at Akmbadur, 600 MW at Mudigubba, and 600 MW at Kolimigundala.

The last date to submit the bids was December 28, 2020. The federation has said many bidders were yet to comprehend the technical aspects of the proposed projects. There is a shortage of time to submit the bids after the pre-bid meeting held on December 14.

In its letter, NSEFI  said developers would first need to visit the site and analyze the topography, as it is one of the essential factors that impact the project cost. “Unless the site is analyzed from all perspectives, the developer cannot estimate the right cost which needs to be factored into the model to determine the tariff at which the bid has to be submitted,” the letter adds.

Subrahmanyam Pulipaka, the chief executive officer of NSEFI, also said that the government’s decision to revoke the power purchase agreements (PPAs) signed for operational wind and solar projects in the state has adversely affected investor sentiment.

According to NSEFI, the projects were developed by independent power producers (IPPs) backed by international and domestic lenders. This has made them apprehensive about participation in the current bidding process.

Recently, NSEFI and the Indian Wind Power Association wrote to the High Court of Andhra Pradesh urging it to expedite hearings for issues renewable projects developers have with PPA and payment delays. They said writ appeals relating to outstanding invoice payments at the tariff signed in the PPA by state distribution companies (DISCOMs) have been pending since December 2019.

“While the matter is listed before the High Court of Andhra Pradesh, getting this issue resolved will be key to attracting large investors (domestic and international) and help boost the confidence of developers to bid for these projects,” the letter added.

Pulipaka requested APGECL  to extend the time for submission of bids by three months, by which time the pending issues related to the PPAs of operational wind and solar projects can also be resolved, and all the stakeholders could work together.

In July this year, NSEFI requested the Union Power Minister R.K. Singh to set aside ₹50 billion (~$666.2 million) from DISCOMs’ liquidity package for Andhra Pradesh so that their dues can be paid to renewable generators.

Previously, Mercom reported that NSEFI had requested the Power Minister to bail out solar generators from the renewable energy disputes in Andhra Pradesh. It had said that solar projects in the state have been suffering due to rampant curtailment of solar generation since July 2019.

According to Mercom’s India Solar Project Tracker, Andhra Pradesh currently has 3.7 GW of large-scale solar projects in operation, while around 1.3 GW of projects is under different stages of development. According to Mercom’s India Solar Tender Tracker, Andhra Pradesh has so far floated 6.5 GW of solar tenders.

RELATED POSTS