Maharashtra DISCOM Gets Regulatory Approval to Procure 111 MW of Solar Power

The Commission ruled that 'Change in Law' claims cannot be made before PPAs are signed

thumbnail

The Maharashtra Electricity Regulatory Commission (MERC) recently approved the procurement of 111 MW of power from grid-connected solar projects under the ‘Mukhyamantri Saur Krishi Vahini Yojana.’

The Commission allowed the Maharashtra State Electricity Distribution Company Limited (MSEDCL) to enter into power purchase agreements (PPAs) with the successful bidders for 25 years. The power procured from these projects would be eligible for fulfilling the solar renewable purchase obligation (RPO).

MSEDCL had filed a petition seeking approval for long-term procurement of 111 MW of power from projects of 2 MW to 10 MW capacity connected to the distributed network.

Background

In its order on December 18, 2020, the Commission had allowed MSEDCL to select bidders at a ceiling tariff of ₹3.30 (~$0.044)/kWh. Later, the distribution company (DISCOM) decided to float the tenders with a revised ceiling tariff of ₹3.05 (~$0.041)/kWh for a cumulative capacity of 1,300 MW.

As per the guidelines released by the Ministry of New and Renewable Energy (MNRE), MSEDCL floated 30 district-wise tenders on April 22, 2021, for power procurement through competitive bidding. A total of 35 bids for 15 districts were received with a total cumulative bidding capacity of 115 MW.

MSEDCL requested the Commission to adopt the tariffs for 111 MW of solar power discovered through the competitive bidding process. The solar generators raised the issue of disruption in the supply of solar equipment from China and the increase in the Goods and Services Tax (GST). The generators requested the Commission to recognize the events as ‘force majeure.’

The generators contended that the Ministry of Finance increased the GST on the import of solar modules and solar inverters from 5% to 12% in September. The last date of bid submission was June 11, 2021. Hence, it should be considered a ‘Change in Law’ event.

MSEDCL said that since the PPAs were yet to be signed, it was premature to seek the declaration of the disruptions in manufacturing capacity in China as a ‘force majeure’ event.

Commission’s analysis

The Commission observed that MSEDCL had conducted a transparent bidding process to procure solar power. MSEDCL had sought approval for the request for selection (RfS), and the PPA documents floated during this bidding process. However, the Commission approved such documents on December 18, 2020, with certain changes. MSEDCL had not highlighted any deviation that required the Commission’s approval in the present case.

The Commission said that the present petition’s scope was limited to tariff adoption, and it had never received a request earlier for approval of a ‘Change in Law’ event along with a tariff adoption petition.

The generators had cited the Appellate Tribunal for Electricity (APTEL) decision in another application in which it had stated that the ‘Change in Law’ can be recognized at the time of tariff adoption.

However, in that judgment, even after a specific query from the APTEL, the parties concerned were not able to point out any provisions which prohibit approval of the ‘Change in Law’ along with the tariff adoption process. However, in the present matter, MSEDCL has objected explicitly to such approval as PPAs were yet to be signed, the Commission said.

It said that the PPA was a prerequisite for power procurement. In the present case, MSEDCL would execute the PPAs with the respective generators only after the tariff adoption order was issued.

While no valid PPAs existed between the parties based on which claims of ‘Change in Law’ could be made, the generators would be eligible to claim compensation for the increase in GST once they incurred such additional expenses.

Last December, MERC issued allowed MSEDCL to float open tenders for its solar projects under the Mukhyamantri Saur Krishi Vahini Yojana.

Earlier, MERC had approved the PPAs for grid-connected solar projects of 235 MW capacity.

Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

RELATED POSTS