EPC Tender Floated for a 14 MW Solar Project at GETCO Substation in Gujarat
The last date to submit the bids online is June 6, 2022
May 17, 2022
Gujarat State Electricity Corporation (GSECL) has invited bids for the design, engineering, supply & procurement, construction, erection, testing, and commissioning of a 14 MW grid-connected solar power project at the Vasundhara substation of the Gujarat Energy Transmission Corporation (GETCO) in the Morbi district.
The successful bidder will also have to take care of the operation and maintenance activities of the project for five years.
The scope of work includes 66 kV underground cable or overhead linework from the solar project to the GETCO 66 KV substation and construction, erection, testing, and commissioning of the complete 66 kV bay and busbar extension.
The last date to submit the bids online is June 6, 2022. Bids will be opened on June 13.
The estimated cost of the tender is ₹560 million (~$7.21 million).
Bidders will have to submit an amount equivalent to ₹5.6 million (~$72,072) as an earnest money deposit.
The successful bidder should furnish a security deposit cum performance bank guarantee of 5% of the EPC contract price within seven working days of the letter of intent.
The bidder should have designed, supplied, erected, supervised, and commissioned MW scale grid-connected solar power projects of cumulative installed capacity (in MW) of 20% or higher of the total bid capacity.
Out of the capacity mentioned above, at least one project should have been 5% or higher (in MW) of the total bid capacity. The reference project of minimum capacity must have been in operation for at least six months before the bid opening date.
The cumulative turnover of the bidder for the last three financial years should be at least ₹40 million (~$514,800) X 14 X 0.7 = ₹392 million (~$5.05 million).
The bidder’s net worth should be positive during the last financial year. The net worth should be calculated as follows: Net Worth = (Equity + Reserves) – (Revaluation reserves + Intangible assets + Miscellaneous expenses to the extent not written off + Carried forward losses).
If the bidder is a 100% subsidiary company and does not satisfy the turnover criteria on its own, its holding company would be required to meet the turnover requirements.
The technology offered should be commercially established, and at least one project based on the technology should be operational for at least one year in India.
The solar modules should be of 72 cell configuration with a rated power of module ≥ 300 Wp as certified for solar module power performance test prescribed by the latest edition of IEC 61215 and IEC 61730 and tested by the Ministry of New and Renewable Energy (MNRE) recognized test laboratory.
Modules should carry a performance warranty of > 90% during the first ten years and > 80% during the next 15 years.
Recently, GSECL issued a request for proposal from engineering, procurement, and construction contractors to install and commission a 2 MW grid-connected solar power project at Utran power station in Gujarat.
Earlier, GSECL had invited bids for the design, engineering, supply, procurement, construction, erection, testing, and commissioning of 27 MW of grid-connected solar power projects around the substations of GETCO at Sitagadh (15 MW) and Kuntalpur (12 MW) in the Surendranagar district.
According to Mercom’s India Solar Tender Tracker, GSECL has issued EPC tenders for 1.8 GW of solar capacity to date.