MNRE Extends Implementation Timeline for 40 GW of Solar Parks in India

Delay in Setting up Transmission System for Solar Projects will Now Attract a Penalty

According to the latest notification issued by the Ministry of New and Renewable Energy (MNRE), any delay in the scheduled commissioning date of solar projects due to unavailability of internal ...
/ / Markets & Policy, Solar
MNRE Amends Guidelines for Selection of Solar Park Developers

MNRE Amends Guidelines for Selection of Solar Park Developers

The Ministry of New and Renewable Energy (MNRE) has amended the guidelines for the selection of solar power park developers (SPPDs) through tariff-based competitive bidding process. The MNRE has amended ...
TEDA Invites Expression of Interest for the Development of 500 MW Solar Park in Tamil Nadu

TEDA Invites Expression of Interest for the Development of 500 MW Solar Park in Tamil Nadu

The Tamil Nadu Energy Development Agency (TEDA) has invited expressions of interest (EoIs) for the development of 500 MW solar park in the state. The bid-submission deadline is June 7, ...