Tariff for a Delayed, Partially Synchronized Rooftop Solar System Slashed by 46%

Tariff for a Delayed, Partially Synchronized Rooftop Solar System Slashed by 46%

The Karnataka Electricity Regulatory Commission (KERC) has issued directions for a new power purchase agreement (PPA) to be signed for a 1 MW rooftop solar power system at a revised ...
Rajasthan Regulator Asks DISCOM to Ensure Timely Payments to Solar and Wind Generators

Rajasthan Regulator Asks DISCOM to Ensure Timely Payments to Solar and Wind Generators

The Rajasthan Electricity Regulatory Commission (RERC) has issued an order directing the Jodhpur Vidyut Vitran Nigam Limited (JdVVNL) to verify and pay its overdue late payment surcharges (LPS) to a ...
Reduced Late Payment Surcharges, A Double Whammy for Power Generators_

Reduced Late Payment Surcharges, A Double Whammy for Power Generators?

To reduce the financial burden of distribution companies (DISCOMs), the Ministry of Power (MoP) proposed a reduction in late payment surcharges (LPS) for payment delays to the power generators last ...
/ / Grid, Market & Policy
Tamil Nadu Commission Directs State DISCOM to Pay ₹6.7 Million in Wind Energy Dues

Tamil Nadu Commission Directs State DISCOM to Pay ₹6.7 Million in Wind Energy Dues

The Tamil Nadu State Electricity Regulatory Commission (TNERC) has ordered the Tamil Nadu Generation and Distribution Company (TANGEDCO) to pay wind generators ₹6.69 million (~$91,586) along with interest at 1% ...
/ / Other, Wind
Maharashtra Commission Asks DISCOM to Clear Dues of Wind Power Generators

Maharashtra Commission Asks DISCOM to Clear Dues of Wind Power Generators

The Maharashtra Electricity Regulatory Commission (MERC) has directed the Maharashtra State Electricity Distribution Company Limited (MSEDCL) to reconcile differences in its outstanding dues with wind generators in the state and ...