CERC Upholds Solar Developers’ Compensation Claims Under Change in Law due to GST

CERC Upholds Solar Developers’ Compensation Claims Under Change in Law due to GST

The Central Electricity Regulatory Commission (CERC) has reiterated that solar developers are entitled to compensation due to the higher expenses incurred after the Goods and Services Tax (GST) came into ...
/ / Markets & Policy, Solar
CERC Allows Compensation to Solar Developers Under Change in Law due to GST

CERC Allows Compensation to Solar Developers Under Change in Law due to GST

The Central Electricity Regulatory Commission (CERC) has ruled that solar developers are entitled to compensation in lieu of higher expenses incurred after the Goods and Services Tax (GST) came into ...
/ / Markets & Policy, Solar
Developer Penalized for Cutting of Trees to Set Up a Solar Project in Rajasthan

Developer Penalized for Cutting of Trees to Set Up a Solar Project in Rajasthan

The National Green Tribunal recently directed a developer to plant ten times more trees than what was cut to develop a solar power project in the Jodhpur district of Rajasthan ...
/ / Markets & Policy, Solar
Wind Energy Generator's Compensation Plea Rejected by Maharashtra Regulator

Wind Energy Generator’s Compensation Plea Rejected by Maharashtra Regulator

Maharashtra Electricity Regulatory Commission (MERC) has rejected a wind power generator’s petition seeking compensation from the Maharashtra State Electricity Distribution Company (MSEDCL) for the power it injected from March 25, ...
/ / Wind
SECI Asked to Reimburse Solar Developer’s GST Claims

SECI Asked to Reimburse Solar Developer’s GST Claims

The Central Electricity Regulatory Commission (CERC) recently directed the Solar Energy Corporation of India (SECI) to compensate a solar developer for the additional cost incurred due to the imposition of ...
/ / Markets & Policy, Solar
CERC Directs SECI to Compensate Solar Developer for Safeguard Duty Claims

CERC Directs SECI to Compensate Solar Developer for Safeguard Duty Claims

The Central Electricity Regulatory Commission (CERC) recently ruled that a solar developer was entitled to compensation for the additional expense incurred due to the imposition of safeguard duty. The Commission ...
/ / Markets & Policy, Solar
CERC Directs SECI to Compensate Solar Developer for GST Claims

CERC Directs SECI to Compensate Solar Developer for GST Claims

The Central Electricity Regulatory Commission (CERC) recently directed the Solar Energy Corporation of India (SECI) to compensate a solar developer for the additional cost incurred due to the imposition of ...
/ / Markets & Policy, Solar
Regulator Upholds APTEL Ruling, Directs DISCOM to Compensate Solar Developers

Regulator Upholds APTEL Ruling, Directs DISCOM to Compensate Solar Developers

The Maharashtra Electricity Regulatory Commission (MERC), in a recent order, asked the Maharashtra State Electricity Distribution Company Limited (MSEDCL) to compensate two solar developers for the additional cost incurred due ...
/ / Grid, Market & Policy
Solar Developers Directed to Mutually Settle Safeguard Duty Claims with SECI

Solar Developers Directed to Mutually Settle Safeguard Duty Claims with SECI

The Central Electricity Regulatory Commission (CERC), in a recent ruling, directed the solar developers to approach the procurers to mutually settle the ‘Change in Law’ claims on account of the ...
/ / Markets & Policy, Solar
DISCOMs Asked to Compensate Solar Developer for GST Claims

DISCOMs Asked to Compensate Solar Developer for GST Claims

The Karnataka Electricity Regulatory Commission (KERC), in a recent order, ruled in favor of a solar developer and directed four distribution companies (DISCOMs) of the state to compensate the developer ...
/ / Markets & Policy, Solar
Solar Developer Asked to Resolve ‘Change in Law’ Claims With the Power Procurers

Solar Developer Asked to Resolve ‘Change in Law’ Claims With the Power Procurers

The Central Electricity Regulatory Commission (CERC) recently ruled that the solar developers must settle the ‘Change in Law’ claims mutually with the power procurers and approach the Commission only for ...
/ / Markets & Policy, Solar
Karnataka Commission Asks BESCOM to Compensate Solar Developer for GST Claims

Karnataka Commission Asks BESCOM to Compensate Solar Developer for GST Claims

The Karnataka Electricity Regulatory Commission (KERC) recently ruled in favor of a solar developer and allowed compensation for four solar projects of 20 MW each on the grounds of the ...
/ / Markets & Policy, Solar
CERC Asks Solar Power Generator and Procurers to Settle ‘Change in Law’ Claims Mutually

CERC Asks Solar Power Generator and Procurers to Settle ‘Change in Law’ Claims Mutually

The Central Electricity Regulatory Commission (CERC) recently ruled that power generators and procurers should mutually settle claims under the ‘Change in Law’ provisions. The central regulator said that the affected ...
/ / Markets & Policy, Solar
Karnataka DISCOM Asked to Compensate Solar Project Developer for GST Claims

Karnataka DISCOM Asked to Compensate Solar Project Developer for GST Claims

The Karnataka Electricity Regulatory Commission (KERC) recently ruled in favor of Adani Green Energy (UP) and directed the Bangalore Electricity Supply Company (BESCOM) to compensate the solar project developer for ...
/ / Markets & Policy, Solar
CERC Directs SECI and Solar Developers to Settle ‘Change in Law’ Claims Mutually

CERC Directs SECI and Solar Developers to Settle ‘Change in Law’ Claims Mutually

The Central Electricity Regulatory Commission (CERC) recently ruled that the affected parties should settle the ‘Change in Law’ claims mutually as per the terms of the power purchase agreement (PPA) ...
/ / Markets & Policy, Solar
APTEL Asks DISCOM to Consider Carrying Cost With Solar Safeguard Duty Refund

APTEL Asks DISCOM to Consider Carrying Cost With Solar Safeguard Duty Refund

The Appellate Tribunal for Electricity (APTEL) recently set aside an order of the Maharashtra Electricity Regulatory Commission (MERC) restricting compensation to two solar developers under the 'Change in Law' clause ...
/ / Markets & Policy, Solar
Solar Developer Allowed GST Compensation on Change in Law Grounds

Solar Developer Allowed GST Compensation on ‘Change in Law’ Grounds

The Central Electricity Regulatory Commission (CERC) recently directed Madhya Pradesh Power Management Company Limited (MPPMCL) and Delhi Metro Rail Corporation (DMRC) to compensate a solar developer for the additional cost ...
/ / Markets & Policy, Solar
Karnataka DISCOMs Asked to Compensate Solar Developer for Safeguard Duty Imposition

Karnataka DISCOMs Asked to Compensate Solar Developer for Safeguard Duty Imposition

The Karnataka Electricity Regulatory Commission (KERC) has recently ruled that five special purpose vehicles (SPVs) of ACME Solar were entitled to levelized incremental tariffs to compensate for the additional cost ...
/ / Markets & Policy, Solar
CERC Directs SECI To Compensate Solar Developer for GST Claims

CERC Directs SECI to Compensate Solar Developer for GST Claims

The Central Electricity Regulatory Commission (CERC), in a recent order, directed the Solar Energy Corporation of India (SECI) to compensate a solar developer for the additional cost incurred due to ...
/ / Markets & Policy, Solar
CERC Reserves Judgment on Solar Developer’s Safeguard Duty Compensation Plea

CERC Reserves Judgment on Solar Developer’s Safeguard Duty Compensation Plea

The Central Electricity Regulatory Commission (CERC), in a recent order, directed Phelan Energy India RJ, a solar developer, to file its response for the delay of 161 days in seeking ...
SECI Asked to Compensate Solar Developer for GST and Safeguard Duty Impact

SECI Asked to Compensate Solar Developer for GST and Safeguard Duty Impact

The Central Electricity Regulatory Commission (CERC), in a recent ruling, directed the Solar Energy Corporation of India (SECI) to compensate a solar developer for the increase in cost incurred due ...
Solar Generator’s Plea to Get Compensation for Power Supplied Over 19% CUF Turned Down

Solar Generator’s Plea to Get Compensation for Power Supplied Over 19% CUF Turned Down

The Tamil Nadu Electricity Regulatory Commission (TNERC) has rejected a solar power generator’s petition seeking compensation for power supplied over the contracted amount. It directed the developer to limit annual ...
Tariffs to be Adjusted within 30 Days of Change in Law Event, Proposes Ministry of Power

Tariffs to be Adjusted within 30 Days of Change in Law Event, Proposes Ministry of Power

The Ministry of Power (MoP) has drafted new electricity rules to make the compensation process easier for renewable project developers. The proposed regulations, if implemented precisely, will bring a huge ...
SECI and NTPC to Pay GST Compensation to Adani Solar’s SPVs

SECI and NTPC to Pay GST Compensation to Adani Solar’s SPVs

The Central Electricity Regulatory Commission (CERC) recently passed an order asking Solar Energy Corporation of India (SECI) and National Thermal Power Corporation (NTPC) to pay the requested compensation to Wardha ...
Delhi Residents May Soon be Paid for Unscheduled Power Cuts

Delhi Residents May Soon be Paid for Unscheduled Power Cuts

The Lieutenant Governor (LG) of Delhi, Anil Baijal, has approved the proposal put forward by the Aam Aadmi Party (AAP) government regarding compensation for residents in case of unscheduled power cuts ...