Two Solar Projects Citing ‘Force Majeure’ Get Commissioning Deadline Extension

Two Solar Projects Citing ‘Force Majeure’ Get Commissioning Deadline Extension

The Karnataka Electricity Regulatory Commission (KERC) recently condoned the delay in commissioning two solar projects of 20 MW each. It extended the scheduled commercial operation dates for both the projects ...
/ / Markets & Policy, Solar
Regulator Dismisses Solar Developer’s Plea for Respite Under Force Majeure

Regulator Dismisses Solar Developer’s Plea for Respite Under Force Majeure

The Karnataka Electricity Regulatory Commission (KERC) dismissed Adani Green Energy (UP) Limited’s plea for relief under the force majeure clause in its power purchase agreement (PPA) with the Gulbarga Electricity ...