The Karnataka Electricity Regulatory Commission (KERC) has ordered the Bangalore Electricity Supply Company Limited (BESCOM) to take into account the amount of energy generated and injected into the grid by Hindustan Aeronautics Limited (HAL) from June 2, 2016, to July 11, 2016, as banked energy.

Karnataka Commission Rules in Favor of HAL in a Dispute on Banked Wind Energy

The Karnataka Electricity Regulatory Commission (KERC) has ordered the Bangalore Electricity Supply Company Limited (BESCOM) to take into account the amount of energy generated and injected into the grid by ...
/ / Wind
Uttar Pradesh DISCOM Gets Approval to Call for Bids to Procure 400 MW of Hydropower

Small Hydro Project Developer in Maharashtra Gets Relief from DISCOM’s Non-Compliance

In its latest ruling, the Maharashtra Electricity Regulatory Commission (MERC) has provided relief to Mohite Industries, a small hydro project developer of a 10 MW Radhanagari small hydro power project ...
/ / Other, Renewable Energy