Karnataka Extends Existing Tariff Structure for Solar Projects Until March 31, 2021

Karnataka Extends Existing Tariff Structure for Solar Projects Until March 31, 2021

The Karnataka Electricity Regulatory Commission (KERC) has extended the validity of the existing tariff structure determined by the Commission in August 2019. The earlier regulation had expired in April 2020 ...
Karnataka’s Hubballi Smart City Invites Bids for 340 kW of Rooftop Solar Systems (1)

Karnataka’s Hubballi Smart City Invites Bids for 340 kW of Rooftop Solar Systems

The Hubballi-Dharwad Smart City Limited (HDSCL) has invited bids for the development of nearly 340 kW of grid-connected rooftop solar PV projects for selected buildings in different locations owned by ...
APTEL Rules in Favor of Solar Developer, Sets Aside KERC Order Reducing COD Extension

APTEL Rules in Favor of Solar Developer, Sets Aside KERC Order Reducing COD Extension

The Appellate Tribunal for Electricity (APTEL) has allowed an appeal by Azure Sunrise Private Limited (ASPL) (subsidiary of Azure Power Global Limited) and has set aside an order passed by ...
Bengaluru to Empanel Agencies for 30 MW of Rooftop Solar Systems with Net Metering

BESCOM to Empanel Agencies for 30 MW of Rooftop Solar Systems with Net Metering

The Bangalore Electricity Supply Company Limited (BESCOM) has invited expression of interest (EoI) for empaneled agencies to design, supply, install, and commission 30 MW of rooftop solar grid-connected power projects ...
/ / Rooftop, Solar
Torrent Power to Pay Revised Tariff for 750 kW of Rooftop Solar to Surat’s Municipal Body

Torrent Power to Pay Revised Tariff for 750 kW of Rooftop Solar to Surat’s Municipal Body

The Gujarat Electricity Regulatory Commission (GERC) has directed Torrent Power Limited to pay the revised tariffs for rooftop solar projects to the Surat Municipal Corporation (SMC). The new tariffs are ...
/ / Rooftop, Solar
APTEL Asks Tamil Nadu Commission to Review its Tariff Order for Renewables

APTEL Asks Tamil Nadu Commission to Review its Tariff Order for Renewables

The Appellate Tribunal for Electricity (APTEL) has asked the Tamil Nadu Electricity Regulatory Commission’s (TNERC) to pass a new tariff order for power procured from renewable sources. This judgment comes ...
APTEL Orders Karnataka DISCOM to Clear Dues of Azure Power for Solar Supply by November End

APTEL Orders Karnataka DISCOM to Clear Dues of Azure Power for Solar Supply by November End

In a case between Azure Power and Gulbarga Electricity Supply Corporation Limited (GESCOM), the Appellate Tribunal for Electricity (APTEL) has ordered the distribution company (DISCOM) to pay all of its ...
/ / Markets & Policy, Solar
APTEL Stalls DERC from Imposing Penalty on Tata Power DISCOM for RPO Non-Compliance

APTEL Stalls DERC from Imposing Penalty on Tata Power DISCOM for RPO Non-Compliance

The Appellate Tribunal for Electricity (APTEL) has provided relief to the Tata Power Delhi Distribution Limited (TPDDL) after it was penalized by the Delhi Electricity Regulatory Commission (DERC) for not meeting ...
/ / Markets & Policy, Solar
APTEL Comes Down on State Electricity Regulators for Delay in Tariff Revision

APTEL Comes Down on State Electricity Regulators for Delay in Tariff Revision

The Appellate Tribunal for Electricity (APTEL) has directed the state and joint electricity regulatory commissions to explain the delay in the revision of the tariff, lack of payments to the ...
/ / Grid, Market & Policy
APTEL Directs Madhya Pradesh DISCOM To Compensate Biomass Developers for Fixed Costs

APTEL Directs Madhya Pradesh DISCOM To Compensate Biomass Developers for Fixed Costs

In a judgment favoring biomass project developers, the Appellate Tribunal for Electricity (APTEL) has found that in the case of one part tariff, developers cannot be denied fixed cost component ...
/ / Biofuel, Other
Andhra High Court Imposes Stay Order on State’s Move to Reduce Solar & Wind Tariffs

Andhra High Court Imposes Stay Order on State’s Move to Reduce Solar & Wind Tariffs

Andhra Pradesh Southern Power Distribution Company’s (APSPDCL) decision to revise solar and wind tariffs have been dealt another blow. In a significant order that reviewed writ petitions by nine developers, ...
Andhra Pradesh’s Decision to Renegotiate Solar and Wind PPAs Sets Bad Precedent

Andhra Pradesh’s Decision to Renegotiate Solar and Wind PPAs Sets Bad Precedent

In a surprise announcement on July 1, 2019, the Andhra Pradesh government said it was going to review the power purchase agreements (PPAs) signed between the state’s electricity distribution companies ...
Solar Developer Approaches APTEL Against Andhra Govt’s Move to Reduce PPA Tariff

Solar Developer Approaches APTEL Against Andhra Govt’s Move to Reduce PPA Tariff

The ongoing turbulence in the state of Andhra Pradesh regarding the renegotiations of solar and wind PPAs does not appear to be ending anytime soon. In the latest development, a ...
Adani Green Commissions a 50 MW Solar Project in Uttar Pradesh

Adani Green Commissions a 50 MW Solar Project in Uttar Pradesh

Adani Green Energy (UP) Limited, a wholly-owned subsidiary of Adani Green Energy Limited, has commissioned a 50 MW solar PV power project in the state of Uttar Pradesh. The off-taker ...
SECI’s 1.2 GW Solar Tender Oversubscribed by 900 MW

No Additional Surcharge for Captive Power Projects, Rules APTEL in Maharashtra

The Appellate Tribunal for Electricity (APTEL) has ruled that no additional surcharge can be levied on captive users, a ruling that sets aside another order passed by Maharashtra Electricity Regulatory ...
/ / Markets & Policy, Solar
Solar and Renewable Energy Policy Roundup from February 2019

Solar and Renewable Energy Policy Roundup from February 2019

February, the shortest month of the year, witnessed some big announcements for the domestic renewable industry, like the imposition of anti-dumping duty on tempered solar glass and EVA sheets. Here ...
/ / Markets & Policy, Solar
Punjab Issues Deviation Settlement Regulations for Solar and Wind Generation

Contractual Agreement Mandatory for Banking of Energy by Project Developer: APTEL

Provisional interconnection approval by a state load dispatch center is not sufficient for banking of energy by any developer and it will not be responsible for pumping power without any ...
/ / Other, Wind
SECI’s 1.2 GW Solar Tender Oversubscribed by 900 MW

Power Purchase Agreements for 23 MW of Solar Projects Approved in Haryana

The Haryana Electricity Regulatory Commission (HERC) has issued an order approving the power purchase agreements (PPAs) of solar projects totaling 23 MW. The commission was examining a common petition filed ...
/ / Markets & Policy, Solar
Tariff Disputes Threaten to Stall 970 MW of Solar Projects in Karnataka

APTEL Intervenes in Ongoing Solar Tariff Dispute for 970 MW of Projects in Karnataka

 In Karnataka, which is also India’s top solar state, 970 MW of grid-connected solar photovoltaic (PV) projects have been embroiled in a tariff dispute. This situation arose after the procurers ...
/ / Markets & Policy, Solar
APTEL Upholds DERC’s Order in Favor of DISCOMs to Conduct Reverse Auction

APTEL Upholds DERC’s Order in Favor of DISCOMs to Conduct Reverse Auction

The Appellate Tribunal for Electricity (APTEL) in New Delhi has dismissed an instant appeal filed by SunE Solar B.V (a part of Sun Edison group) and upheld an earlier order ...
/ / Markets & Policy, Solar
Interview: Solar & Non-Solar REC Generators Could Lose ₹18 Billion if Relief is Not Provided

Interview: Solar & Non-Solar REC Generators Could Lose ₹18 Billion if Relief is Not Provided

The solar REC trading in the country was stalled for the past one year. In April 2018, both, solar and non-solar renewable energy certificates (REC) were traded for the first ...
/ / Markets & Policy, Solar
CERC Gives its Go-Ahead to Solar and Non-Solar REC Trading

CERC Gives its Go-Ahead to Solar and Non-Solar REC Trading

The Central Electricity Regulatory Commission (CERC) has given its go-ahead for the trade of solar and non-solar Renewable Energy Certificates (RECs) in the country. The new order comes after the ...
/ / Other, Renewable Energy
NLC India May Lose ₹1.36/kWh for 500 MW of Solar Projects Due to Delays in Commissioning

NLC India May Lose ₹1.36/kWh for 500 MW of Solar Projects Due to Delays in Commissioning

Neyveli Lignite Corporation (NLC) India might have to bear a loss of ₹1.36 (~$0.020)/kWh for the 500 MW of grid-connected solar photovoltaic (PV) projects, which are being developed in the ...
/ / Markets & Policy, Solar
Green Energy Association to Appeal APTEL REC Order to the Supreme Court

Green Energy Association to Appeal APTEL REC Order to the Supreme Court

The Green Energy Association has decided to appeal the recent order passed by the Appellate Tribunal of Electricity (APTEL) regarding floor and forbearance prices of Renewable Energy Certificates (RECs). Recently, ...
/ / Other, Renewable Energy
APTEL Dismisses Petitions Against New Solar and Non-Solar REC Pricing Issued by CERC

APTEL Dismisses Petitions Against New Solar and Non-Solar REC Pricing Issued by CERC

The Appellate Tribunal of Electricity (APTEL) has dismissed petitions filed by stakeholders against the issue of new forbearance and floor prices for solar and non-solar renewable energy certificates (RECs) by ...