Regulator Allows Partial Credit Adjustment for an Open Access Wind Power Consumer

The Commission, however, rejected the claim for credit adjustment for June 2016, citing that it was barred by limitation

June 10, 2021

thumbnail

The Maharashtra Electricity Regulatory Commission (MERC), in a recent ruling, allowing for credit adjustment of units generated from wind projects for September 2017, July 2018, and October 2019 for an open access consumer. The Commission, however, rejected the claims of the petitioner for credit adjustment of wind units of June 2016, which was barred by limitation (three years).

Bramhacorp had filed a petition, seeking adjustment of open access credit units for June 2016, September 2017, July 2018, and October 2019, and extend the credits in the subsequent month’s energy bills.

Background

Bramhacorp is a consumer of the Maharashtra State Electricity Distribution Company Limited (MSEDCL), involved in the hotel and restaurant business in Mahabaleshwar. The company is an open access consumer sourcing power from various renewable energy sources.

The company, in its submission, said that MSEDCL had neither denied the adjustment of the units generated from open access wind projects nor adjusted the same.

MSEDCL, in its reply, said that any claim before August 3, 2017, was barred by limitation (three years). Hence, Bramhacorp’s claim for June 2016 was time-barred under the Limitation Act, 1963, and any such claim cannot be adjudicated.

MSEDCL stated that the claim of Bramhacorp for June 2016 was barred by the period of limitation, and for other months, i.e., July 2018 and October 2019, MSEDCL had given the credit adjustments of units in the open access bill. For September 2017, there was no consumption record available against which the open access units credit adjustment could be given.

Commission’s analysis

The Commission observed that during the hearing dated December 28, 2020, it had directed both parties to resolve the issue mutually. Accordingly, both the parties had resolved the issues for July 2018 and October 2019, and Bramhacorp accepted the same.

The Commission noted that for September 2017, wherein MSEDCL has submitted that there was no consumption detail available against which open access unit’s adjustment could be given and hence no adjustment was provided for the said month.

The regulator clarified that the Commission could not adjudicate any claim barred by time limitation. Apparently, in the present case, the petitioner had not made any case under the provisions of the Limitation Act and had merely stated that it was regularly following up with MSEDCL for credit adjustment of wind units.

The Commission further added that claims for credit adjustment of wind units of June 2016 had become time-barred in terms of the Limitation Act in June 2019.

“It is also a settled principle of law that mere correspondence between the contracting parties cannot extend the period of limitation. The aggrieved party has to approach the courts within the period of limitation. Therefore, the Commission rejects the claim for credit adjustment of wind units for June 2016, which is barred by limitation,” the Commission noted.

In April last year, MERC had announced various charges payable by open access consumers for the financial year 2020-21 to 2024-25.

Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

RELATED POSTS

Get the most relevant India solar and clean energy news.

RECENT POSTS