Daily News Wrap-Up: Solar Project Costs Vary by Module Type in Q3 2026
BESCOM revises solar open access billing methodology in Karnataka
November 24, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
In the third quarter (Q3) of calendar year 2026, average system costs for large-scale solar projects varied across module technologies. Costs fell for Indian non-DCR mono PERC and TOPCon modules, while rising for Chinese and Indian DCR modules.
Bangalore Electricity Supply Company (BESCOM) revised the time-of-day billing methodology for high-tension consumers procuring solar and non-solar power through open access. Under the revised methodology, wheeled solar energy can be adjusted only against electricity consumed during off-peak hours.
The Rajasthan High Court ruled against Rajasthan Rajya Vidyut Utpadan Nigam retrospectively imposing a minimum 20% domestic content requirement on developers awarded contracts for 500 MW/2,000 MWh of standalone battery energy storage systems.
West Bengal State Electricity Distribution Company invited bids to set up rooftop solar projects across the state. The projects entail setting up 100 MW of grid-connected rooftop solar projects consisting of 1 kW rooftop solar systems across 100,000 residential consumers through gross metering.
The Central Electricity Regulatory Commission (CERC) granted interstate transmission system (ISTS) charge waiver eligibility to a 150 MW captive solar project at the Phalodi-Pokhran Solar Park in Rajasthan, following delays in the commissioning of the park’s power evacuation infrastructure.
CERC granted ISTS charge waiver eligibility to 166 MW of a 171.6 MW wind-solar hybrid project in Karnataka after delays in commissioning the associated transmission infrastructure.
The Gujarat Electricity Regulatory Commission (GERC) partially allowed a developer’s plea for an extension of the scheduled commercial operation date (SCOD) for a 200 MW wind power project in Gir Somnath district, Gujarat, due to force majeure events.
Noida Power Company announced the winners of its auction to procure 300 MW of round-the-clock power from ISTS-connected renewable energy projects across India. ReNew won 85 MW at ₹4.43 (~$0.0477)/kWh, while Purvah Green Power bagged 215 MW at ₹4.44 (~$0.0478)/kWh, out of the 300 MW quoted capacity.
Enel, through its wholly owned subsidiaries Enel Green Power North America and EGPNA Project Holdco 7, signed an agreement with energyRe to acquire a 317 MW solar portfolio in South Carolina. The portfolio is expected to generate more than 540 GWh of electricity annually after entering service.
The Oman Investment Authority announced the completion of seven projects with a combined investment of OMR 1.6 billion (~$4.17 billion) across the energy, manufacturing, and services sectors. The projects include the United Solar Polysilicon plant in Sohar Free Zone, developed with an investment of OMR 668 million (~$1.74 billion).