CERC Rejects ISTS Charge Waiver Extension for 707 MW Solar, Wind Projects

It ruled that projects commissioned after June 30, 2026, cannot claim the extended waiver

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Central Electricity Regulatory Commission (CERC) has rejected an independent power producer’s (IPP) request to extend the scheduled commercial operation dates (SCOD) of four wind and solar projects totaling 707.3 MW and extend the waiver of interstate transmission system (ISTS) charges.