CERC Allows Developer to Sell 100 MW of Infirm Solar Power Outside Agreement
The Commission rejected a new proposed tariff of ₹3.08/kWh
July 7, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Central Electricity Regulatory Commission (CERC) has allowed a solar developer to continue injecting infirm power from the 100 MW solar component of its 600 MW wind-solar hybrid project and sell the power outside the power purchase agreement (PPA) until partial or early commissioning because the project’s wind component was delayed due to connectivity issues.