APTEL Extends Deadline for 72.6 MW of Uncommissioned Wind Capacity

The Tribunal ordered ₹91.75 million in compensation for delayed commissioning

September 25, 2026

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Appellate Tribunal for Electricity (APTEL) has extended the commissioning deadline for 72.6 MW of a 200 MW wind project in Maharashtra to December 31, 2026, while declining to stay the compensation mechanism imposed for delayed commissioning.