APTEL Extends Commissioning Date for 20 MW Solar Project in Karnataka
The project was delayed due to non-availability of KPTCL 220 kV Kudligi substation
September 10, 2026
Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights
The Appellate Tribunal for Electricity (APTEL) has extended the scheduled commercial operation date (SCOD) for a renewable energy project developer’s 20 MW solar project in Karnataka from November 3, 2019, to May 30, 2020.