The project was delayed due to non-availability of KPTCL 220 kV Kudligi substation

September 10, 2026

thumbnail

Follow Mercom India on WhatsApp for exclusive updates on clean energy news and insights


The Appellate Tribunal for Electricity (APTEL) has extended the scheduled commercial operation date (SCOD) for a renewable energy project developer’s 20 MW solar project in Karnataka from November 3, 2019, to May 30, 2020.