Deadline to Complete Solar Projects Under Component-A of KUSUM Program Extended (1)

State Transmission Utility to Compensate Solar Project Developer for Generation Losses

The Karnataka Electricity Regulatory Commission (KERC) has directed Karnataka Power Transmission Corporation (KPTCL) to compensate a solar project developer for generation losses. KPTCL is directed to pay compensation at ₹4.43 ...
/ / Grid, Grid Optimization
Karnataka Regulator Reduces Tariff for a 20 MW Delayed Solar Project

Karnataka Regulator Reduces Tariff for a 20 MW Delayed Solar Project

The Karnataka Electricity Regulatory Commission (KERC), in a recent order, ruled that ACME Kudligi Solar was liable for a reduced tariff of 80% of the quoted tariff and liquidated damages ...
Karnataka Regulator Approves Tariff of ₹8.40/kWh for a Delayed Solar Power Project

Karnataka Regulator Approves Tariff of ₹8.40/kWh for a Delayed Solar Project

The Karnataka Electricity Regulatory Commission (KERC) has approved a tariff of ₹8.40 (~$0.115)/kWh as per the power purchase agreement (PPA) signed between Bangalore Electricity Supply Company Limited (BESCOM) and the ...
/ / Markets & Policy, Solar
CERC Set to Hear Adani Solar’s Petition Against Curtailment in Karnataka

CERC Set to Hear Adani Solar’s Petition Against Power Curtailment in Karnataka

The Central Electricity Regulatory Commission (CERC) accepted the petition filed by Wardha Solar and Parampujya Solar, asking to ensure the ‘must-run’ status of renewable projects in Karnataka. Background Earlier, Wardha ...
Karnataka Mini-Hydro Projects Can Carry Forward Banked Energy for 2 Months

Karnataka Mini-Hydro Projects Can Carry Forward Banked Energy for 2 Months

The Karnataka Electricity Regulatory Commission (KERC) has approved a request to carry forward the banked energy from mini-hydropower generators as of May 31, 2020, to July 31, 2020. Any banked ...
/ / Other, Water
Adani Green to Receive Refund of ₹1.2 Million for a 20 MW Solar Project in Mysuru

Adani Green to Receive Refund of ₹1.2 Million for a 20 MW Solar Project in Mysuru

The Karnataka Electricity Regulatory Commission (KERC) has ordered that Adani Green Energy Limited (AGEL) should get a refund of ₹1.2 million (~$15,754) from the Gulbarga Electricity Supply Company Limited (GESCOM) ...
/ / Solar, Utility Scale
Karnataka Electricity Regulator Reduces Tariff for a Delayed 10 MW Solar Project

Karnataka Electricity Regulator Reduces Tariff for a Delayed 10 MW Solar Project

The Karnataka Electricity Regulatory Commission (KERC) has dismissed a petition by Shorapur Solar Power Limited that argued its 10 MW solar project was delayed due to force majeure (unforeseeable) events ...
After Tamil Nadu, NSEFI Writes to Karnataka About Solar Projects Facing Curtailment

After Tamil Nadu, NSEFI Writes to Karnataka About Solar Projects Facing Curtailment

In Karnataka, India’s top state in terms of installed solar photovoltaic (PV) capacity, solar PV projects are facing issues of curtailment. The National Solar Energy Federation of India (NSEFI) has ...
KERC Dismisses Petition Claiming Interest for Delayed Payment for a Biomass Project

KERC Dismisses Petition Claiming Interest for Delayed Payment for a Biomass Project

In a recent order, Karnataka Electricity Regulatory Commission (KERC) has dismissed a petition filed by  Koppal Green Power Limited against Gulbarga Electricity Supply Company Limited (GESCOM) asking it to pay ...
/ / Other, Waste to Energy
Punjab Issues Deviation Settlement Regulations for Solar and Wind Generation

Contractual Agreement Mandatory for Banking of Energy by Project Developer: APTEL

Provisional interconnection approval by a state load dispatch center is not sufficient for banking of energy by any developer and it will not be responsible for pumping power without any ...
/ / Other, Wind
NTPC Issues Fresh Tender for 20 MW Floating Solar at its Gas Power Plant in Uttar Pradesh

Karnataka Invites Expression of Interest to Install Three Floating Solar Projects

The Karnataka Urban Water Supply and Drainage Board has invited expression of interest (EoI) to set up floating solar power projects over reservoirs in Manvi, Sirguppa, and Ballari City. The ...
/ / Floating Solar, Solar
Karnataka Solar Policy: State Revises Solar Installation Target to 6,000 MW by March 2021

Karnataka Solar Policy: State Revises Solar Installation Target to 6,000 MW by March 2021

The government of Karnataka has announced amendments to the Karnataka State Solar Policy 2014-21. The estimated solar energy potential of the state has been updated from 20 GW to 24.7 GW ...
/ / Markets & Policy, Solar